Introduction
Usually, a life cycle analysis is done for certain products or services to investigate its environmental impacts. In this case, we want to examine a rather complex matter: the remodelling of a park and its long-term consequences.
This tutorial is also available as a PDF.
The functional unit
When designing a life cycle analysis you always start by defining your functional unit. Since we want to compare influences on nature and environment of a procedure, the reshaping of a public park area, it is a bit tricky. Basically, we need to create two different life cycle analyses, one for the original and one for the remodelled park, so the functional unit could be called "9000m2 of public park area".
The object
The Sellerpark, with its about 9000 m2 [2], is located between the urban districts Mitte and Wedding in northwest Berlin. It is bordered by a four-lane street and the Schifffahrtskanal, an artificial waterway. It also contains the estuary of the brook Panke.
For 50 years the Sellerpark developed quite unnoticed. Trees and bushes grew wildly and there was a lot of space in the embankments for ducks and birds for undisturbed breeding. By mid 2009 the park was completely reconstructed: 59 of the 102 trees were, due to security reasons, chopped down, most of the bushes were removed and a big granite terrace with 4 levels was built around the estuary.
All of this wouldn’t be that dramatic if the money for the project, altogether EUR 660’000 [3], wouldn’t be part of a fund for the compensation of other interferences in nature. In Germany it is mandatory to rebuild the same amount of biosphere that was not able to be saved in course of a construction process [4] [5]. In this case EUR 130’000 [6] was to be used for the compensation of a newly built road in neighboring district Moabit.
System boundaries
Creating a Life Cycle Analysis, one should always be sure of its capabilities. The case study about Sellerpark is now written two years after its actual transformation. Due to this, we have to deal with quite a lot of approximations. Size of trees, used machines, terrestrial modulations and some other processes can only be guessed or estimated. Nevertheless we are sure to be able to give a good clue about the environmental impact. The precision of the method is also limited through the data sets. We are concentrating on certain aspects of the remodelling (the terrace, the wood alteration, etc.), thus we are only able to reconstruct the process partly.
At last, this study has a rather exemplary character, showing the functions and capabilities of the software and sharing an interesting case of urban eco-management.
Model description
As already mentioned, we only want to concentrate on the most influential aspects of the remodelling. On the one hand, one analysis will be made for a theoretical untouched park: The development of the natural cover within 50 years before and 20 years after the alteration, plus some work that is usually done in order to keep a park as it is (regular mowing). On the other hand, we will calculate for the remodelled park: the deforestation, the building of the terrace and also the diminished capability of CO2 fixation due to reduced tree crop will be incorporated. Finally we will compare the two analyses in respect to their long-term Carbon dioxide fixation and the one-time environmental impacts of the reconstruction.
The Software and database
This case study will be performed with openLCA, an open source Life Cycle Analysis Software. Datasets are collected in the Ecoinvent database which offers reliable data for most of the processes and used products.
openLCA is a really easy-to-use open source Software. Most of the handling will be familiar to you, if you are used to the drag-and-drop mechanisms of MS Windows. You can gain insight into the handling of openLCA at the webpage: openLCA documentation.
In combination with a substantial and detailed database like Ecoinvent you can easily build up a wide scale of processes just by creating your own processes, extracting basic information out of the database, connect and quantify them and finally let the system add up all of its environmental impacts. Due to the complexity of Ecoinvent there can be a huge number of inputs and outputs into the nature by the end of a product’s LCA. Impact analysis (LCIA) can help you then to evaluate your results in respect to the overall impacts on e.g. global warming or acidification.
Biomass
Although there was a great variety in plants that were removed, we will focus only on the deforestation since trees play the major role in the long-term fixation of Carbon dioxide. We know that 59 of the 102 tress of the Sellerpark were cut and 11 were planted instead.
Regarding the fact that the trees were not measured in height and volume we can only use data of an "average" tree. In the following table you will find an overview of parameters, applied locally, i.e. per process. With these factors, we will be able to model the yearly growth of trees and also the quantities (in m3) of trees that were cut. We consider that a new tree (a seedling) will grow slowly (7,25 kg/y) during the first 20 years, and then faster (12,5 kg/y).
| Name | Formula | Description |
|---|---|---|
| density | 402 | Tree density; kg/m3 |
| growthseedling | 7.25 | Growth rate of new trees; kg/y |
| growthtree | 12.5 | Growth rate of trees; kg/y |
| trees | 102 | Total trees; trees |
| cuttrees | 59 | Trees chopped down; trees |
| newtrees | 11 | New trees planted; trees |
| timebefore | 50 | Time before remodelling; year |
| timeafter | 20 | Time after remodelling; year |
| timeseedling | 20 | Time of seedling growth; year |
The deforestation
According to the approximation from above 59 old trees (cottonwood, maple, elm, robinia and lime-tree) were cut down and replaced with 11 new trees. Integrated in the case study should be growth, cut down, chipping, transport and the final waste disposal. Ecoinvent offers a large number of datasets for different kinds of wood, harvesting tools and disposal facilities to choose from.
The mowing
To ensure a safe use of the park, the grass needs to be mowed. The grass area covers approximately 8000m2 and it needs to be done 3 times a year. As some areas are now free under the trees, but also a terrace is set, we will consider that this area stays the same after the remodelling. The following parameters can be considered:
| Name | Formula | Description |
|---|---|---|
| mowingarea | 8000 | Area to be mowed; m2 |
| mowingperyear | 3 | How many time per year is it mowed |
The terrace and seats
On-site research has indicated that approximately 80 m3 of granite have been installed [9]. For the modelling of the terrace we will consider the granite extraction (as an Ecoinvent dataset) along with its transport (manufacturer says from China) and the land-excavation on the spot (only for the terrace, because seats were just laid on the ground). Other building machineries and processes will be neglected due to uncertainty.
openLCA allows to simply quantify masses and transporting distances in order to calculate environmental impacts. The following parameters can be considered:
| Name | Formula | Description |
|---|---|---|
| granitdensity | 2800 | Density of granit; kg/m3 |
| groundhole | 70 | Excavation from the ground; m3 |
| seatsvolume | 10 | Volume of granit for the seats; m3 |
| shipdistance | 19188 | Average distance China-Hamburg; km |
| lorrydistance | 290 | Average distance Hamburg-Berlin; km |
Create and compare models
At first, it seems wise to create a subfolder in each category (flow, process, product system, and project). To do so, right click on the folder and "create a child category" (you can call it "Sellerpark" for example). This way, you can easily store together everything you will create.
The untouched park
Create flows
At first, you need to create a few product flows:
- New park; ref=number of items
- Untouched park; ref=number of items
- Deforestation; ref=number of items
- Grown trees; ref=number of items
- Terrace; ref=number of items
- Seats; ref=number of items
- Natural stone plate, grounded, at site
It might be useful to add also a description, so you can remember they are related to this case study.
Create processes
Two processes need to be created.
Untouched park
- Quantitative reference: Untouched park
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Grown trees | Sellerpark | m3 | (timeseedling*growthseedling +(timebefore-timeseedling)*growthtree+timeafter*growthtree)*trees/density |
| mowing, by motor mower | Agricultural means of production/work processes | m2 | mowingarea*(timebefore+timeafter)*mowingperyear |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Untouched park | Sellerpark | Item(s) | 1 |
Growth
- Quantitative reference: Grown trees
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| hardwood, standing, under bark, in forest | Wooden materials/extraction | m3 | 0.5 |
| softwood, standing, under bark, in forest | Wooden materials/extraction | m3 | 0.5 |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Grown trees | Sellerpark | Item(s) | 1 |
Create a product system
- Name: Park, untouched
- Reference process: Untouched park
- Ensure you tick the 2 options before clicking "Finish".
At the end, your first model should look like this:
The remodelled park
Create processes
As all the flows have already been created, we can directly create new 5 processes. Considering the deforestation as well as the wood growth of old and new trees, the following graph can be considered for the available wood in the park, each year.
Remodelled park
- Quantitative reference: New park
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Deforestation | Sellerpark | Item(s) | (timeseedling*growthseedling+(timebefore-timeseedling)*growthtree)*cuttrees/density |
| Grown trees | Sellerpark | Item(s) | (timeseedling*growthseedling+(timebefore-timeseedling+timeafter)*growthtree)*(trees-cuttrees)/density+timeafter*growthseedling*newtrees/density |
| Terrace | Sellerpark | Item(s) | 1 |
| Seats | Sellerpark | Item(s) | 1 |
| mowing, by motor mower | Agricultural means of production/work processes | m2 | mowingarea*(timebefore +timeafter)*mowingperyear |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| New park | Sellerpark | Item(s) | 1 |
Terrace, building
- Quantitative reference: Terrace
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| excavation, hydraulic digger | construction processes/ civil engineering | m3 | groundhole |
| Natural stone plate, grounded, at site | Sellerpark | kg | groundhole*granitdensity |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Terrace | Sellerpark | Item(s) | 1 |
Seats, building
- Quantitative reference: Seats
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Natural stone plate, grounded, at site | Sellerpark | kg | granitdensity*seatsvolume |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Seats | Sellerpark | Item(s) | 1 |
Natural stone plate, transport
- Quantitative reference: Natural stone plate, grounded, at site
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| natural stone plate, grounded, at regional storage | Construction materials /others | kg | 1 |
| transport, lorry 20-28t, fleet average | transport systems /road | kg*km | lorrydistance |
| transport, transoceanic freight ship | transport systems /ship | kg*km | shipdistance |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Natural stone plate, grounded, at site | Sellerpark | kg | 1 |
Deforestation
- Quantitative reference: Deforestation
- Inputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| hardwood, standing, under bark, in forest | Wooden materials/ extraction | m3 | 0.5 |
| softwood, standing, under bark, in forest | Wooden materials/ extraction | m3 | 0.5 |
| transport, lorry 3.5-7.5t, EURO4 | Transport systems/ road | kg*km | density*50 |
| wood chopping, mobile chopper, in forest | Wooden materials/ extraction | kg | density |
| disposal, wood untreated, 20% water, to municipal incineration | Waste management/ municipal incineration | kg | density |
- Outputs:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Deforestation | Sellerpark | Item(s) | 1 |
NB: The wood, once chopped and chipped is considered as a waste that needs to go to an incineration process. Due to the Ecospold format, openLCA considers waste management processes as input. This allows the deforestation process to bear the whole incineration burden. On the other side, if you plan to calculate a mass balance, this will lead you to false results.
If the incineration process were considered as an output of deforestation, it would not be part of the upstream chain that leads to the functional unit. To rectify this, one should add a service flow, looping back to the deforestation.
Create a product system
- Name: Park, remodelled
- Reference process: Remodelled park
- Ensure you tick the 2 options before clicking "Finish".
At the end, your first model should look like this:
Life Cycle Inventory
After finishing the tree-structured process chain, the system will automatically add up all environmental impacts. The Inventory is a list of all extracted resources (elementary inputs) and emissions (elementary outputs) that are necessary for the functional unit. In our case, we prepared two different Inventories for the same functional unit "9000 m2 of public park area", one remodeled and one untouched.
To do so, simply click on "Results" and calculate. While doing it for each product system, you can reach the list of inputs and outputs of the whole system that looks like this:
NB: Alternatively, these lists can be exported to Excel spreadsheets to be analysed separately.
Life Cycle Impact Analysis
The LC Inventory as shown above is not very manageable. Applying a "Life Cycle Impact Assessment Method" helps evaluating data. Ecoinvent contains the most important LCIA Methods such as eco-indicator 99, IPCC 2001, CML 2001, IMPACT 2002+, a.s.f... In this case study we want to apply two different methods.
One the one hand we want to compare absorbed Carbon dioxide over a set period of time, thus we have to create our own LCIA method:
- Create a new LCIA method called "Carbon fixation";
- Add a LCIA category, name it "Total absorbed carbon dioxide" and Unit=kg;
- Add a LCIA factor and flow as seen below:
This rather easy method weighs every Kilogram of absorbed CO2 with the factor 1. It can now be applied to the two product systems "park, remodelled" and "park, untouched".
- Click on "Results" of both product systems and then select the CO2 fixation method;
- Create a new project called "Sellerpark – CO2 fixation";
- Add the two product systems and save the project;
- Draw a chart with the CO2 fixation method. It should look like this:
About 20% less capability of Carbon Fixation over a period of 70 years, not to mention emissions in course of the construction producing an alarming result, especially taking into account that in this densly populated area, parks and gardens are rather rare.
On the other hand we want to examine the usual ecobalance indicators. "CML 2001" is a well known LCIA method that evaluates the inventory, considering midpoint categories.
- Click on "Results" of both product systems and then select the CML 2001 method;
- Create a new project called "Sellerpark: untouched vs remodelled";
- Add the two product systems and save the project;
- Draw a chart with the CML 2001 method and the following categories:
In all categories, the remodelled park has much bigger impacts than the untouched park. These results proof the doutable character of the remodelling’s good influence on the environment.
NB: In the category "Climate change – GWP 100a", the carbon dioxide saved by the trees is not considered. Otherwise, the value would have been negative.
Modification of the functional unit
Now that results clearly show impacts over a period of 70 years (20 after the remodelling), we can wonder what could it be considering 50 years after the change (a total period of 100 years). To try such new model, only a few steps are necessary.
The untouched park
- Copy, paste and rename the product system "Park, untouched" into "Park, untouched, 100 years";
- In the parameter tab of the product system, add the following data:
| Name | Formula | Description |
|---|---|---|
| timeafter | 50 | Time after remodelling; year |
In openLCA, there is a classification on parameters’ priority. It can be summed up:
Global parameter > Product system parameter > Process parameter
This means that when the LCI will be calculated, the value timeafter=20 from the process will be overwritten by the value timeafter=50.
- Save the change, reload the database and calculate the results.
The remodelled park
It could be done very easily:
- Copy, paste and rename the process "park remodelled";
- Change values of parameters and formulas;
- Create a new product system and it’s done.
But, this is not the nice and funny way! The following method is much more interesting:
- In the process "remodelled park", add the following parameters:
| Name | Formula | Description |
|---|---|---|
| newwood1 | timeafter*growthseedling*newtrees/density | Wood from new trees; if timeafter <=20 years |
| newwood2 | timeseedling*growthseedling*newtrees/density+(timeafter-timeseedling)*growthtree*newtrees/density | Wood from new trees; if timeafter >20 years |
| oldwood | (timeseedling*growthseedling+(timebefore-timeseedling+timeafter)*growthtree)*(trees-cuttrees)/density | Wood from the old trees (m3) |
| totalwood | a1*(oldwood+newwood1)+a2*(oldwood+newwood2) | Sum of old and new wood, depending on timeafter (m3) |
| a1 | 1 | a1=1 when timeafter<=20 years, otherwise 0 |
| a2 | 0 | a2=1 if timeafter>20years, otherwise 0 |
In Input, change this value:
| Flow | Category | Unit | Resulting amount |
|---|---|---|---|
| Grown trees | Sellerpark | m3 | totalwood |
- Save the change;
- Copy, paste and rename the product system "Park, remodelled" into "Park, remodelled, 100 years";
- In the parameter tab of the product system, add the following data:
| Name | Formula | Description |
|---|---|---|
| timeafter | 50 | Time after remodelling; year |
| a1 | 0 | a1=1 when timeafter<=20 years, otherwise 0 |
| a2 | 1 | a2=1 if timeafter>20years, otherwise 0 |
- Save the change, reload the database and calculate the results.
NB: Please, make sure you understand the calculations and the logic behind!
Comparison
- Create new projects to analyse the CO2 fixation and the eight CML 2001 categories.
Impacts of the eight categories give slightly the same results (in the same proportion as before). The CO2 fixation difference is ever bigger (almost 30%) between the two models as it was in the previous comparison.
As the time period has been changed and the results are still fairly the same, we can consider that the original assumptions are true.
Analysis
So, why is there a so big difference between these two models? Thanks to the Sankey diagram, we will be able to find it out:
- Open the process "Park, remodelled, 100 years", calculate the results and open the "Analysis" with the "CML 2001" method;
- On tab "Sankey diagram", display it for "Human toxicity – HTP 100a" and "Terrestrial ecotoxicity – TAETP 100a" with 5% cut off:
Regarding these two categories, impacts come mainly from the production and the transport of the granite from China to Germany. These effects are not local (i.e. only in Berlin), but worldwide, thus they are globally distributed.
Conclusion
As expected, the remodeling of the Sellerpark has vast impacts on nature and environment. That is indeed an interesting fact for a biotope compensation project.
Anyway, this case study is rather to demonstrate the capabilities of this LCA software than to judge over absurdity of communal park development. We tried to account for the most environmentally influential aspect of the process. Certainly there are a number of other parts of the remodeling (other plants than trees, newly built park lanes, etc.) that contribute to impacts. From our point of view this neglect may not alter the overall result significantly.
Since the Sellerpark project is already some time ago, we had to juggle with a great number of unknowns – the results may thus differ from reality (which cannot be verified as the "untouched park" has never existed"). Nevertheless it is possible, in line with good preparation, on-site monitoring and accurate measurement, to solve these unknowns and thus create a 100% resilient Eco Balance.
References
- ↑ 1.0 1.1 Suzanne Torka, MoabitOnline (http://www.moabitonline.de)
- ↑ FIS-Broker, Interactive maps, Berlin (http://www.stadtentwicklung.berlin.de/geoinformation/fis-broker)
- ↑ Press release, City of Berlin (http://www.berlin.de/ba-mitte/aktuell/presse/archiv/20081002.0955.110750.html)
- ↑ http://www.stadtentwicklung.berlin.de/umwelt/landschaftsplanung/bbe/download/bbe_leit.pdf
- ↑ http://www.buzer.de/gesetz/8972/index.htm
- ↑ Townhall meeting, Moabit, protocol (http://www.lehrter-strasse-berlin.net/dateien/BR-Lehrter_Protokolle/2006/BRL-Prot_2006-05-02.pdf)
- ↑ MoabitOnline http://www.lehrter-strasse-berlin.net/dateien/Gruen/Sellerpark_Entw-mit-Persp.pdf
- ↑ 8.0 8.1 GreenDeltaTC (http://www.greendeltatc.com)
- ↑ On-site measurements
See also
- Viticulture: conventional vs organic. A case study using the ecoinvent database
- Beer bottle: Aluminium can vs PET bottle. A case study using the free NREL database
- Remodelling of a park: the Sellerpark in Berlin. A case study of urban eco-management using the ecoinvent database